Midwest Mole mobilized to the project site and began the microtunnel installation of the 48″ diameter Hobas pipe. As of…
October progress consisted of receiving delivery of the 48″ diameter hobas jacking pipe. Completion of the launch pit and the…
Work completed in September included installation of geotechnical monitoring instrumentation, dewatering, temporary electric service, and excavation of the launch and…
Field work commenced in July and August after geotechnical investigation and earth retention system engineering was completed. Progress for the…