April’s progress consisted of completing the connecting structure manhole barrel, box tunnel backfilling and pipe connections in the receiving pit.…
In March, significant progress was made with the successful completion of the cast-in-place concrete connecting structure. Additionally, the 48″ diameter…
February Progress consisted of completing the exterior wall wall core and threading the 48″ HOBAS pipe into the 72″ casing.…
Happy New Year! The progress of January consisted of Rausch Infrastructure preparing the launch pit for Midwest Mole to set…
Microtunneling was completed with the successful daylighting at the receiving pit. Midwest Mole began demobilizing their microtunneling equipment and will…
Midwest Mole mobilized to the project site and began the microtunnel installation of the 48″ diameter Hobas pipe. As of…
October progress consisted of receiving delivery of the 48″ diameter hobas jacking pipe. Completion of the launch pit and the…
Work completed in September included installation of geotechnical monitoring instrumentation, dewatering, temporary electric service, and excavation of the launch and…
Field work commenced in July and August after geotechnical investigation and earth retention system engineering was completed. Progress for the…