Skip to content
MWRD Westchester Pumping Station Relief
MWRD Westchester Pumping Station Relief
MWRD Contract No. 21-168-3S
  • Home
  • About
  • News
  • Contact Us

Author: Rausch Infrastructure

April Progress Update

June 10, 2025 Rausch Infrastructure Leave a comment

April’s progress consisted of completing the connecting structure manhole barrel, box tunnel backfilling and pipe connections in the receiving pit.…

Continue Reading →

March Progress Update

April 11, 2025 Rausch Infrastructure

In March, significant progress was made with the successful completion of the cast-in-place concrete connecting structure. Additionally, the 48″ diameter…

Continue Reading →

February Progress Update

March 13, 2025 Rausch Infrastructure

February Progress consisted of completing the exterior wall wall core and threading the 48″ HOBAS pipe into the 72″ casing.…

Continue Reading →

January Progress Update

Rausch Infrastructure

Happy New Year! The progress of January consisted of Rausch Infrastructure preparing the launch pit for Midwest Mole to set…

Continue Reading →

December Progress Update

January 9, 2025 Rausch Infrastructure

Microtunneling was completed with the successful daylighting at the receiving pit. Midwest Mole began demobilizing their microtunneling equipment and will…

Continue Reading →

November Progress Update

December 4, 2024 Rausch Infrastructure

Midwest Mole mobilized to the project site and began the microtunnel installation of the 48″ diameter Hobas pipe. As of…

Continue Reading →

October Progress Update

November 11, 2024 Rausch Infrastructure

October progress consisted of receiving delivery of the 48″ diameter hobas jacking pipe. Completion of the launch pit and the…

Continue Reading →

September Progress Update

October 9, 2024 Rausch Infrastructure

Work completed in September included installation of geotechnical monitoring instrumentation, dewatering, temporary electric service, and excavation of the launch and…

Continue Reading →

August 2024 Update

September 26, 2024 Rausch Infrastructure

Field work commenced in July and August after geotechnical investigation and earth retention system engineering was completed. Progress for the…

Continue Reading →

Recent Posts

  • April Progress Update
  • March Progress Update
  • February Progress Update
  • January Progress Update
  • December Progress Update
  • Starting: Spring 2024
  • Estimated Completion: Fall 2024
  • Contractor: Rausch Infrastructure, LLC
  • Contact: Anthony Rausch 708-667-0165
  • 24-Hour Hotline 331-481-9317
Copyright © 2025 MWRD Westchester Pumping Station Relief