December Progress Update

Microtunneling was completed with the successful daylighting at the receiving pit.

Midwest Mole began demobilizing their microtunneling equipment and will return to the site in January to begin casing installation for the upcoming connection to the Westchester Pump Station.

Rausch completed the excavation of soil fill in the Westchester Pump Station in preparation for the connection to pump station.