October Progress Update

October progress consisted of receiving delivery of the 48″ diameter hobas jacking pipe. Completion of the launch pit and the installation of all ground monitoring prior to the start of microtunneling. Receiving pit is nearly complete.

Damage to a 24″ sanitary sewer that was in close proximity to the launch pit was also repaired.